Upgrading hydrogen generator

UAB "Vilniaus energija"

Old electrolyzers SEU-10 were dismantled in Power Station No 3 of UAB Vilniaus Energija. They were replaced by Hogen electrolyzers, which were commissioned and staff training was performed. To ensure the efficiency of the new units, a reverse osmosis water treatment system was installed. The new electrolyzer has a capacity of 4 nm3/h x 2.

The following equipment was delivered, installed, commissioned and handed over for operation:

  • The old electrolyzers SEU-10 were dismantled.
  • Hogen electrolyzers were selected, installed, commissioned, and staff training was performed.
  • To ensure the efficiency of the new units, a reverse osmosis water treatment system was installed.
2005
year started
7
month of implementation
2005
year of project delivery