UAB “Ekobana” Is Carrying Out the Construction of the 110/6 kV Drūkšiai Transformer Substation

2025 DEC 02

UAB “Ekobana” is carrying out construction works of the 110/6 kV Dr?kšiai transformer substation. On December 1 of this year, transformer T-1 together with the 6 kV switchgear was successfully energized.

The commissioning of the second transformer is planned for mid-January.